Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman

While the concepts of planning and scheduling seem to be adequately discussed in the project management literature, relatively few examples of factors specifically affecting the performance of planning and scheduling are to be found. The study reported in this paper investigated a set of factors...

Full description

Bibliographic Details
Main Authors: Nasseri, Hammad Al, Aulin, Radhlinah
Format: Article
Language:English
Published: Penerbit Universiti Sains Malaysia 2016
Subjects:
Online Access:http://eprints.usm.my/41449/
http://eprints.usm.my/41449/1/JCDC_21%282%29_Art_1%281-20%29.pdf
_version_ 1848879292499361792
author Nasseri, Hammad Al
Aulin, Radhlinah
author_facet Nasseri, Hammad Al
Aulin, Radhlinah
author_sort Nasseri, Hammad Al
building USM Institutional Repository
collection Online Access
description While the concepts of planning and scheduling seem to be adequately discussed in the project management literature, relatively few examples of factors specifically affecting the performance of planning and scheduling are to be found. The study reported in this paper investigated a set of factors identified as enablers and barriers to successful project planning and scheduling of construction projects in Oman. The study adopted a questionnaire-based survey to measure the impact of each factor. The data were analysed using the relative impact (or importance) index (RII). On the basis of RII rankings, the results revealed that the identified enablers and barriers were all considered significant. This could imply that all of the factors should be considered equally from the perspective of project planning and scheduling, including schedule control. In addition, the results suggest that project managers should pay attention to the more significant barriers to mitigate their potential impacts on planning and scheduling. Recommendations for mitigating those barriers are presented. The study provides useful insights into the impact of various factors on the planning and scheduling performance of construction projects in Oman and how improvement might be achieved.
first_indexed 2025-11-15T17:44:55Z
format Article
id usm-41449
institution Universiti Sains Malaysia
institution_category Local University
language English
last_indexed 2025-11-15T17:44:55Z
publishDate 2016
publisher Penerbit Universiti Sains Malaysia
recordtype eprints
repository_type Digital Repository
spelling usm-414492018-08-21T01:34:16Z http://eprints.usm.my/41449/ Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman Nasseri, Hammad Al Aulin, Radhlinah TH1-9745 Building construction While the concepts of planning and scheduling seem to be adequately discussed in the project management literature, relatively few examples of factors specifically affecting the performance of planning and scheduling are to be found. The study reported in this paper investigated a set of factors identified as enablers and barriers to successful project planning and scheduling of construction projects in Oman. The study adopted a questionnaire-based survey to measure the impact of each factor. The data were analysed using the relative impact (or importance) index (RII). On the basis of RII rankings, the results revealed that the identified enablers and barriers were all considered significant. This could imply that all of the factors should be considered equally from the perspective of project planning and scheduling, including schedule control. In addition, the results suggest that project managers should pay attention to the more significant barriers to mitigate their potential impacts on planning and scheduling. Recommendations for mitigating those barriers are presented. The study provides useful insights into the impact of various factors on the planning and scheduling performance of construction projects in Oman and how improvement might be achieved. Penerbit Universiti Sains Malaysia 2016 Article PeerReviewed application/pdf en http://eprints.usm.my/41449/1/JCDC_21%282%29_Art_1%281-20%29.pdf Nasseri, Hammad Al and Aulin, Radhlinah (2016) Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman. Journal of Construction in Developing Countries , 21 (2). pp. 1-20. ISSN 1823-6499 http://web.usm.my/jcdc/vol21_2_2016/JCDC%2021(2)_Art%201(1-20).pdf
spellingShingle TH1-9745 Building construction
Nasseri, Hammad Al
Aulin, Radhlinah
Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
title Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
title_full Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
title_fullStr Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
title_full_unstemmed Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
title_short Enablers and Barriers to Project Planning and Scheduling Based on Construction Projects in Oman
title_sort enablers and barriers to project planning and scheduling based on construction projects in oman
topic TH1-9745 Building construction
url http://eprints.usm.my/41449/
http://eprints.usm.my/41449/
http://eprints.usm.my/41449/1/JCDC_21%282%29_Art_1%281-20%29.pdf