Causes and effects of delays in Malaysian construction industry

The problem of delays in the construction industry is a global phenomenon and the construction industry in Malaysia is no exception. The main purpose of this study is to identify the delay factors and their impact (effect) on project completion. Earlier studies either considered the causes or the ef...

Full description

Bibliographic Details
Main Authors: Sambasivan, Murali, Soon, Yau Wen
Format: Article
Language:English
Published: Elsevier 2007
Online Access:http://psasir.upm.edu.my/id/eprint/40276/
http://psasir.upm.edu.my/id/eprint/40276/1/Causes%20and%20effects%20of%20delays%20in%20Malaysian%20construction%20industry.pdf
_version_ 1848849379296804864
author Sambasivan, Murali
Soon, Yau Wen
author_facet Sambasivan, Murali
Soon, Yau Wen
author_sort Sambasivan, Murali
building UPM Institutional Repository
collection Online Access
description The problem of delays in the construction industry is a global phenomenon and the construction industry in Malaysia is no exception. The main purpose of this study is to identify the delay factors and their impact (effect) on project completion. Earlier studies either considered the causes or the effects of project delays, separately. This study takes an integrated approach and attempts to analyze the impact of specific causes on specific effects. A questionnaire survey was conducted to solicit the causes and effects of delay from clients, consultants, and contractors. About 150 respondents participated in the survey. This study identified 10 most important causes of delay from a list of 28 different causes and 6 different effects of delay. Ten most important causes were: (1) contractor’s improper planning, (2) contractor’s poor site management, (3) inadequate contractor experience, (4) inadequate client’s finance and payments for completed work, (5) problems with subcontractors, (6) shortage in material, (7) labor supply, (8) equipment availability and failure, (9) lack of communication between parties, and (10) mistakes during the construction stage. Six main effects of delay were: (1) time overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment. This study has also established an empirical relationship between each cause and effect.
first_indexed 2025-11-15T09:49:27Z
format Article
id upm-40276
institution Universiti Putra Malaysia
institution_category Local University
language English
last_indexed 2025-11-15T09:49:27Z
publishDate 2007
publisher Elsevier
recordtype eprints
repository_type Digital Repository
spelling upm-402762015-09-15T06:52:21Z http://psasir.upm.edu.my/id/eprint/40276/ Causes and effects of delays in Malaysian construction industry Sambasivan, Murali Soon, Yau Wen The problem of delays in the construction industry is a global phenomenon and the construction industry in Malaysia is no exception. The main purpose of this study is to identify the delay factors and their impact (effect) on project completion. Earlier studies either considered the causes or the effects of project delays, separately. This study takes an integrated approach and attempts to analyze the impact of specific causes on specific effects. A questionnaire survey was conducted to solicit the causes and effects of delay from clients, consultants, and contractors. About 150 respondents participated in the survey. This study identified 10 most important causes of delay from a list of 28 different causes and 6 different effects of delay. Ten most important causes were: (1) contractor’s improper planning, (2) contractor’s poor site management, (3) inadequate contractor experience, (4) inadequate client’s finance and payments for completed work, (5) problems with subcontractors, (6) shortage in material, (7) labor supply, (8) equipment availability and failure, (9) lack of communication between parties, and (10) mistakes during the construction stage. Six main effects of delay were: (1) time overrun, (2) cost overrun, (3) disputes, (4) arbitration, (5) litigation, and (6) total abandonment. This study has also established an empirical relationship between each cause and effect. Elsevier 2007-07 Article PeerReviewed application/pdf en http://psasir.upm.edu.my/id/eprint/40276/1/Causes%20and%20effects%20of%20delays%20in%20Malaysian%20construction%20industry.pdf Sambasivan, Murali and Soon, Yau Wen (2007) Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25 (5). pp. 517-526. ISSN 0263-7863; ESSN: 1873-4634 http://www.sciencedirect.com/science/article/pii/S0263786306001700 10.1016/j.ijproman.2006.11.007
spellingShingle Sambasivan, Murali
Soon, Yau Wen
Causes and effects of delays in Malaysian construction industry
title Causes and effects of delays in Malaysian construction industry
title_full Causes and effects of delays in Malaysian construction industry
title_fullStr Causes and effects of delays in Malaysian construction industry
title_full_unstemmed Causes and effects of delays in Malaysian construction industry
title_short Causes and effects of delays in Malaysian construction industry
title_sort causes and effects of delays in malaysian construction industry
url http://psasir.upm.edu.my/id/eprint/40276/
http://psasir.upm.edu.my/id/eprint/40276/
http://psasir.upm.edu.my/id/eprint/40276/
http://psasir.upm.edu.my/id/eprint/40276/1/Causes%20and%20effects%20of%20delays%20in%20Malaysian%20construction%20industry.pdf