Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia

The Certificate of Completion and Compliance (CCC) was implemented in April 2007. The Certificate of Completion and Compliance is a certificate that confirms that a building is eligible and safe to occupy, issued by the main person who submits it. Most of the housing projects fail to hand over the b...

Full description

Bibliographic Details
Main Authors: Noraziah Mohammad Zin, Aishah Samsudin, Suhana Johar, Mazlan Mohd Tahir
Format: Article
Language:English
Published: Penerbit Universiti Kebangsaan Malaysia 2023
Online Access:http://journalarticle.ukm.my/23500/
http://journalarticle.ukm.my/23500/1/39.pdf
_version_ 1848815863533142016
author Noraziah Mohammad Zin,
Aishah Samsudin,
Suhana Johar,
Mazlan Mohd Tahir,
author_facet Noraziah Mohammad Zin,
Aishah Samsudin,
Suhana Johar,
Mazlan Mohd Tahir,
author_sort Noraziah Mohammad Zin,
building UKM Institutional Repository
collection Online Access
description The Certificate of Completion and Compliance (CCC) was implemented in April 2007. The Certificate of Completion and Compliance is a certificate that confirms that a building is eligible and safe to occupy, issued by the main person who submits it. Most of the housing projects fail to hand over the building to the buyer within a set time period such as in the sale and purchase agreement caused by the failure to issue a completion certificate and compliance. This study aims to identify the causes of delays in issuing certificates of completion and compliance for housing projects in Malaysia. Qualitative methods through literature review have been used to identify the processes of issuing certificates of completion and compliance (CCC) of housing projects in Malaysia and to identify the causes of delays in issuing certificates of completion and compliance (CCC). Next, a questionnaire was conducted on 141 respondents to identify the causes of delays in issuing Certificates of Completion and Compliance (CCC) for housing projects in Malaysia. The results of the literacy study found that 18 causes of delay in the issuance of completion and compliance certificates. The findings found that the main contributors to the delay in issuing completion certificates and compliance for housing projects in Malaysia are caused by developers, consultants, contractors, local authorities, external technical agencies and others.
first_indexed 2025-11-15T00:56:44Z
format Article
id oai:generic.eprints.org:23500
institution Universiti Kebangasaan Malaysia
institution_category Local University
language English
last_indexed 2025-11-15T00:56:44Z
publishDate 2023
publisher Penerbit Universiti Kebangsaan Malaysia
recordtype eprints
repository_type Digital Repository
spelling oai:generic.eprints.org:235002024-05-10T03:40:47Z http://journalarticle.ukm.my/23500/ Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia Noraziah Mohammad Zin, Aishah Samsudin, Suhana Johar, Mazlan Mohd Tahir, The Certificate of Completion and Compliance (CCC) was implemented in April 2007. The Certificate of Completion and Compliance is a certificate that confirms that a building is eligible and safe to occupy, issued by the main person who submits it. Most of the housing projects fail to hand over the building to the buyer within a set time period such as in the sale and purchase agreement caused by the failure to issue a completion certificate and compliance. This study aims to identify the causes of delays in issuing certificates of completion and compliance for housing projects in Malaysia. Qualitative methods through literature review have been used to identify the processes of issuing certificates of completion and compliance (CCC) of housing projects in Malaysia and to identify the causes of delays in issuing certificates of completion and compliance (CCC). Next, a questionnaire was conducted on 141 respondents to identify the causes of delays in issuing Certificates of Completion and Compliance (CCC) for housing projects in Malaysia. The results of the literacy study found that 18 causes of delay in the issuance of completion and compliance certificates. The findings found that the main contributors to the delay in issuing completion certificates and compliance for housing projects in Malaysia are caused by developers, consultants, contractors, local authorities, external technical agencies and others. Penerbit Universiti Kebangsaan Malaysia 2023 Article PeerReviewed application/pdf en http://journalarticle.ukm.my/23500/1/39.pdf Noraziah Mohammad Zin, and Aishah Samsudin, and Suhana Johar, and Mazlan Mohd Tahir, (2023) Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia. Jurnal Kejuruteraan, SI-6 (1). pp. 483-493. ISSN 0128-0198 https://www.ukm.my/jkukm/si-6-1-2023/
spellingShingle Noraziah Mohammad Zin,
Aishah Samsudin,
Suhana Johar,
Mazlan Mohd Tahir,
Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia
title Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia
title_full Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia
title_fullStr Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia
title_full_unstemmed Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia
title_short Punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (CCC) projek perumahan di Malaysia
title_sort punca-punca kelewatan pengeluaran perakuan siap dan pematuhan (ccc) projek perumahan di malaysia
url http://journalarticle.ukm.my/23500/
http://journalarticle.ukm.my/23500/
http://journalarticle.ukm.my/23500/1/39.pdf