A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation

The purpose of this study is to investigate the effect of lead time variability on Material Requirements Planning (MRP) performance. This study attempts to understand the impact of lead time variability in order to provide insight in dealing with lead time uncertainty in MRP system. Thus, this study...

Full description

Bibliographic Details
Main Author: Ting, Leslie Sze Hin
Format: Dissertation (University of Nottingham only)
Language:English
Published: 2012
Online Access:https://eprints.nottingham.ac.uk/25880/
_version_ 1848793073130143744
author Ting, Leslie Sze Hin
author_facet Ting, Leslie Sze Hin
author_sort Ting, Leslie Sze Hin
building Nottingham Research Data Repository
collection Online Access
description The purpose of this study is to investigate the effect of lead time variability on Material Requirements Planning (MRP) performance. This study attempts to understand the impact of lead time variability in order to provide insight in dealing with lead time uncertainty in MRP system. Thus, this study aims to investigate the effect of lead time variability at different production level and examine the effectiveness of safety lead time in dealing with lead time uncertainty. In this study, a series of experiments are conducted. The experiments begin with single lead time variability at different production level (i.e. bottleneck process/common required component, lowest BOM level, first BOM level and end item) with varying levels of lead time variability (i.e. low lead time variability and high lead time variability or moderate lead time variability). Then the experiments are extended to multiple lead time variability at the same production level (i.e. lowest BOM level and first BOM level). Safety lead time of one day (Safety Lead Time = 1 and Safety Lead Time = -1) is applied at bottleneck process/common required component in attempt to improve MRP performance. The findings show that common lead time has the greatest impact on MRP performance and therefore it is the first thing manufacturers should deal with. Safety lead time does not improve MRP performance in this case even if optimal safety lead time is applied.
first_indexed 2025-11-14T18:54:30Z
format Dissertation (University of Nottingham only)
id nottingham-25880
institution University of Nottingham Malaysia Campus
institution_category Local University
language English
last_indexed 2025-11-14T18:54:30Z
publishDate 2012
recordtype eprints
repository_type Digital Repository
spelling nottingham-258802018-02-03T05:44:03Z https://eprints.nottingham.ac.uk/25880/ A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation Ting, Leslie Sze Hin The purpose of this study is to investigate the effect of lead time variability on Material Requirements Planning (MRP) performance. This study attempts to understand the impact of lead time variability in order to provide insight in dealing with lead time uncertainty in MRP system. Thus, this study aims to investigate the effect of lead time variability at different production level and examine the effectiveness of safety lead time in dealing with lead time uncertainty. In this study, a series of experiments are conducted. The experiments begin with single lead time variability at different production level (i.e. bottleneck process/common required component, lowest BOM level, first BOM level and end item) with varying levels of lead time variability (i.e. low lead time variability and high lead time variability or moderate lead time variability). Then the experiments are extended to multiple lead time variability at the same production level (i.e. lowest BOM level and first BOM level). Safety lead time of one day (Safety Lead Time = 1 and Safety Lead Time = -1) is applied at bottleneck process/common required component in attempt to improve MRP performance. The findings show that common lead time has the greatest impact on MRP performance and therefore it is the first thing manufacturers should deal with. Safety lead time does not improve MRP performance in this case even if optimal safety lead time is applied. 2012-09-21 Dissertation (University of Nottingham only) NonPeerReviewed application/pdf en https://eprints.nottingham.ac.uk/25880/1/Dissertation_4170468.pdf Ting, Leslie Sze Hin (2012) A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation. [Dissertation (University of Nottingham only)] (Unpublished)
spellingShingle Ting, Leslie Sze Hin
A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation
title A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation
title_full A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation
title_fullStr A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation
title_full_unstemmed A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation
title_short A Study of Interactions between Lead Time Variability and Material Requirements Planning (MRP) performance VIA Simulation
title_sort study of interactions between lead time variability and material requirements planning (mrp) performance via simulation
url https://eprints.nottingham.ac.uk/25880/