Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City

When implementing a project in the field, it is fairly uncommon for numerous projects to be delayed or even halted. This also has an impact on project cost escalation, resulting in project losses. Earned value analysis can help manage construction projects efficiently and effectively. The results va...

Full description

Bibliographic Details
Main Author: Tezar Aulia, Rachman
Format: Article
Language:English
English
Published: INTI International University 2024
Subjects:
Online Access:http://eprints.intimal.edu.my/1947/
http://eprints.intimal.edu.my/1947/2/484
http://eprints.intimal.edu.my/1947/3/joit2024_02b.pdf
_version_ 1848766879311593472
author Tezar Aulia, Rachman
author_facet Tezar Aulia, Rachman
author_sort Tezar Aulia, Rachman
building INTI Institutional Repository
collection Online Access
description When implementing a project in the field, it is fairly uncommon for numerous projects to be delayed or even halted. This also has an impact on project cost escalation, resulting in project losses. Earned value analysis can help manage construction projects efficiently and effectively. The results value analysis was done to estimate the extent to which the project was carried out according to the work plan. This assessment was performed on the Aranaway Kiram Bridge Construction project in Banjarbaru City. The project was aimed to determine weekly time performance and project completion time. The method employed was earned value analysis. According to the results of the analysis method (earned value analysis), the results from the 3rd to the 18th week experienced delays, as evidenced by the performance of the Schedule Variance (SV) which was Negative (-) and the Schedule Performance Index (SPI) which was less than 1, but work accelerated in the 19th week of the Banjarbaru City Aranaway Kiram Bridge Construction Project, as evidenced by the SV performance which was Positive (+) and SPI greater than 1. The research results estimated the project's completion time as 253 days.
first_indexed 2025-11-14T11:58:09Z
format Article
id intimal-1947
institution INTI International University
institution_category Local University
language English
English
last_indexed 2025-11-14T11:58:09Z
publishDate 2024
publisher INTI International University
recordtype eprints
repository_type Digital Repository
spelling intimal-19472025-06-13T02:16:33Z http://eprints.intimal.edu.my/1947/ Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City Tezar Aulia, Rachman T Technology (General) TA Engineering (General). Civil engineering (General) TG Bridge engineering When implementing a project in the field, it is fairly uncommon for numerous projects to be delayed or even halted. This also has an impact on project cost escalation, resulting in project losses. Earned value analysis can help manage construction projects efficiently and effectively. The results value analysis was done to estimate the extent to which the project was carried out according to the work plan. This assessment was performed on the Aranaway Kiram Bridge Construction project in Banjarbaru City. The project was aimed to determine weekly time performance and project completion time. The method employed was earned value analysis. According to the results of the analysis method (earned value analysis), the results from the 3rd to the 18th week experienced delays, as evidenced by the performance of the Schedule Variance (SV) which was Negative (-) and the Schedule Performance Index (SPI) which was less than 1, but work accelerated in the 19th week of the Banjarbaru City Aranaway Kiram Bridge Construction Project, as evidenced by the SV performance which was Positive (+) and SPI greater than 1. The research results estimated the project's completion time as 253 days. INTI International University 2024-07 Article PeerReviewed text en cc_by_4 http://eprints.intimal.edu.my/1947/2/484 text en cc_by_4 http://eprints.intimal.edu.my/1947/3/joit2024_02b.pdf Tezar Aulia, Rachman (2024) Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City. Journal of Innovation and Technology, 2024 (02). pp. 1-7. ISSN 2805-5179 http://ipublishing.intimal.edu.my/joint.html
spellingShingle T Technology (General)
TA Engineering (General). Civil engineering (General)
TG Bridge engineering
Tezar Aulia, Rachman
Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City
title Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City
title_full Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City
title_fullStr Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City
title_full_unstemmed Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City
title_short Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City
title_sort time performance analysis using earned value on the construction of the aranaway kiram bridge in banjar baru city
topic T Technology (General)
TA Engineering (General). Civil engineering (General)
TG Bridge engineering
url http://eprints.intimal.edu.my/1947/
http://eprints.intimal.edu.my/1947/
http://eprints.intimal.edu.my/1947/2/484
http://eprints.intimal.edu.my/1947/3/joit2024_02b.pdf