Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City
When implementing a project in the field, it is fairly uncommon for numerous projects to be delayed or even halted. This also has an impact on project cost escalation, resulting in project losses. Earned value analysis can help manage construction projects efficiently and effectively. The results va...
| Main Author: | |
|---|---|
| Format: | Article |
| Language: | English English |
| Published: |
INTI International University
2024
|
| Subjects: | |
| Online Access: | http://eprints.intimal.edu.my/1947/ http://eprints.intimal.edu.my/1947/2/484 http://eprints.intimal.edu.my/1947/3/joit2024_02b.pdf |
| _version_ | 1848766879311593472 |
|---|---|
| author | Tezar Aulia, Rachman |
| author_facet | Tezar Aulia, Rachman |
| author_sort | Tezar Aulia, Rachman |
| building | INTI Institutional Repository |
| collection | Online Access |
| description | When implementing a project in the field, it is fairly uncommon for numerous projects to be delayed or even halted. This also has an impact on project cost escalation, resulting in project losses. Earned value analysis can help manage construction projects efficiently and effectively. The results value analysis was done to estimate the extent to which the project was carried out according to the work plan. This assessment was performed on the Aranaway Kiram Bridge Construction project in Banjarbaru City. The project was aimed to determine weekly time performance and project completion time. The method employed was earned value analysis. According to the results of the analysis method (earned value analysis), the results from the 3rd to the 18th week experienced delays, as evidenced by the performance of the Schedule Variance (SV) which was Negative (-) and the Schedule Performance Index (SPI) which was less than 1, but work accelerated in the 19th week of the Banjarbaru City Aranaway Kiram Bridge Construction Project, as evidenced by the SV performance which was Positive (+) and SPI greater than 1. The research results estimated the project's completion time as 253 days. |
| first_indexed | 2025-11-14T11:58:09Z |
| format | Article |
| id | intimal-1947 |
| institution | INTI International University |
| institution_category | Local University |
| language | English English |
| last_indexed | 2025-11-14T11:58:09Z |
| publishDate | 2024 |
| publisher | INTI International University |
| recordtype | eprints |
| repository_type | Digital Repository |
| spelling | intimal-19472025-06-13T02:16:33Z http://eprints.intimal.edu.my/1947/ Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City Tezar Aulia, Rachman T Technology (General) TA Engineering (General). Civil engineering (General) TG Bridge engineering When implementing a project in the field, it is fairly uncommon for numerous projects to be delayed or even halted. This also has an impact on project cost escalation, resulting in project losses. Earned value analysis can help manage construction projects efficiently and effectively. The results value analysis was done to estimate the extent to which the project was carried out according to the work plan. This assessment was performed on the Aranaway Kiram Bridge Construction project in Banjarbaru City. The project was aimed to determine weekly time performance and project completion time. The method employed was earned value analysis. According to the results of the analysis method (earned value analysis), the results from the 3rd to the 18th week experienced delays, as evidenced by the performance of the Schedule Variance (SV) which was Negative (-) and the Schedule Performance Index (SPI) which was less than 1, but work accelerated in the 19th week of the Banjarbaru City Aranaway Kiram Bridge Construction Project, as evidenced by the SV performance which was Positive (+) and SPI greater than 1. The research results estimated the project's completion time as 253 days. INTI International University 2024-07 Article PeerReviewed text en cc_by_4 http://eprints.intimal.edu.my/1947/2/484 text en cc_by_4 http://eprints.intimal.edu.my/1947/3/joit2024_02b.pdf Tezar Aulia, Rachman (2024) Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City. Journal of Innovation and Technology, 2024 (02). pp. 1-7. ISSN 2805-5179 http://ipublishing.intimal.edu.my/joint.html |
| spellingShingle | T Technology (General) TA Engineering (General). Civil engineering (General) TG Bridge engineering Tezar Aulia, Rachman Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City |
| title | Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City |
| title_full | Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City |
| title_fullStr | Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City |
| title_full_unstemmed | Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City |
| title_short | Time Performance Analysis Using Earned Value on the Construction of the Aranaway Kiram Bridge in Banjar Baru City |
| title_sort | time performance analysis using earned value on the construction of the aranaway kiram bridge in banjar baru city |
| topic | T Technology (General) TA Engineering (General). Civil engineering (General) TG Bridge engineering |
| url | http://eprints.intimal.edu.my/1947/ http://eprints.intimal.edu.my/1947/ http://eprints.intimal.edu.my/1947/2/484 http://eprints.intimal.edu.my/1947/3/joit2024_02b.pdf |