Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru)

In construction management, there are various stages of problems in terms of managing the project budget, so it is necessary to have a design or estimation of the project budget by analyzing construction costs. Currently, service providers tend not to fully calculate unit price analysis based on SNI...

Full description

Bibliographic Details
Main Authors: Hendra, Cahyadi, Gusti, Maysarah, Abdurrahman, .
Format: Article
Language:English
English
Published: INTI International University 2024
Subjects:
Online Access:http://eprints.intimal.edu.my/1946/
http://eprints.intimal.edu.my/1946/1/joit2024_01.pdf
http://eprints.intimal.edu.my/1946/2/483
_version_ 1848766879048400896
author Hendra, Cahyadi
Gusti, Maysarah
Abdurrahman, .
author_facet Hendra, Cahyadi
Gusti, Maysarah
Abdurrahman, .
author_sort Hendra, Cahyadi
building INTI Institutional Repository
collection Online Access
description In construction management, there are various stages of problems in terms of managing the project budget, so it is necessary to have a design or estimation of the project budget by analyzing construction costs. Currently, service providers tend not to fully calculate unit price analysis based on SNI analysis but rather on their own analysis or previous experience in completing construction work. Based on this, it is necessary to compare unit price analysis between the SNI method and field data. This study aims to determine the unit prices in the field and compare the price differences between the SNI 2022 method and field data in the National Land Agency Building Construction Project in Banjarbaru. The results of this analysis show that the price based on SNI 2022 analysis is Rp368,900,072.55, while the price based on field observations is IDR 269,231,757.50. Based on the analysis results of both methods, the cost difference between the SNI 2022 analysis and the actual field conditions for the National Land Agency Building Construction Project in Banjarbaru is IDR 99,668,315.02.
first_indexed 2025-11-14T11:58:09Z
format Article
id intimal-1946
institution INTI International University
institution_category Local University
language English
English
last_indexed 2025-11-14T11:58:09Z
publishDate 2024
publisher INTI International University
recordtype eprints
repository_type Digital Repository
spelling intimal-19462025-01-15T02:32:00Z http://eprints.intimal.edu.my/1946/ Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru) Hendra, Cahyadi Gusti, Maysarah Abdurrahman, . T Technology (General) TA Engineering (General). Civil engineering (General) TH Building construction In construction management, there are various stages of problems in terms of managing the project budget, so it is necessary to have a design or estimation of the project budget by analyzing construction costs. Currently, service providers tend not to fully calculate unit price analysis based on SNI analysis but rather on their own analysis or previous experience in completing construction work. Based on this, it is necessary to compare unit price analysis between the SNI method and field data. This study aims to determine the unit prices in the field and compare the price differences between the SNI 2022 method and field data in the National Land Agency Building Construction Project in Banjarbaru. The results of this analysis show that the price based on SNI 2022 analysis is Rp368,900,072.55, while the price based on field observations is IDR 269,231,757.50. Based on the analysis results of both methods, the cost difference between the SNI 2022 analysis and the actual field conditions for the National Land Agency Building Construction Project in Banjarbaru is IDR 99,668,315.02. INTI International University 2024-07 Article PeerReviewed text en cc_by_4 http://eprints.intimal.edu.my/1946/1/joit2024_01.pdf text en cc_by_4 http://eprints.intimal.edu.my/1946/2/483 Hendra, Cahyadi and Gusti, Maysarah and Abdurrahman, . (2024) Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru). Journal of Innovation and Technology, 2024 (01). pp. 1-6. ISSN 2805-5179 http://ipublishing.intimal.edu.my/joint.html
spellingShingle T Technology (General)
TA Engineering (General). Civil engineering (General)
TH Building construction
Hendra, Cahyadi
Gusti, Maysarah
Abdurrahman, .
Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru)
title Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru)
title_full Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru)
title_fullStr Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru)
title_full_unstemmed Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru)
title_short Comparison Analysis of Unit Prices for Reinforced Concrete Column Work using the 2022 Indonesian National Standard (Sni) Method and Field Data (An Empirical Study On the Construction Project of the National Land Agency Building in Banjarbaru)
title_sort comparison analysis of unit prices for reinforced concrete column work using the 2022 indonesian national standard (sni) method and field data (an empirical study on the construction project of the national land agency building in banjarbaru)
topic T Technology (General)
TA Engineering (General). Civil engineering (General)
TH Building construction
url http://eprints.intimal.edu.my/1946/
http://eprints.intimal.edu.my/1946/
http://eprints.intimal.edu.my/1946/1/joit2024_01.pdf
http://eprints.intimal.edu.my/1946/2/483