Mining truck scheduling with stochastic maintenance cost

Open pit mining operations utilize large scale and expensive equipment. For the mines implementing shovel and truck operation system, trucks constitute a large portion of these equipment and are used for hauling the mined materials. In order to have sustainable and viable operation, these equipment...

Full description

Bibliographic Details
Main Authors: Topal, Erkan, Ramazan, S.
Format: Journal Article
Published: Zhongguo Meitan Xuehui 2012
Online Access:http://hdl.handle.net/20.500.11937/49389
_version_ 1848758230168109056
author Topal, Erkan
Ramazan, S.
author_facet Topal, Erkan
Ramazan, S.
author_sort Topal, Erkan
building Curtin Institutional Repository
collection Online Access
description Open pit mining operations utilize large scale and expensive equipment. For the mines implementing shovel and truck operation system, trucks constitute a large portion of these equipment and are used for hauling the mined materials. In order to have sustainable and viable operation, these equipment need to be utilized efficiently with minimum operating cost. Maintenance cost is a significant proportion of the overall operating costs. The maintenance cost of a truck changes non-linearly depending on the type, age and truck types. A new approach based on stochastic integer programming (SIP) techniques is used for annually scheduling a fixed fleet of mining trucks in a given operation, over the life of mine (multi-year time horizon) to minimize maintenance cost. The maintenance cost data in mining usually has uncertainty caused from the variability of the operational conditions at mines. To estimate the cost, usually historic data from different operations for new mines, and/or the historic data at the operating mines are used. However, maintenance cost varies depending on road conditions, age of equipment and many other local conditions at an operation. Traditional models aim to estimate the maintenance cost as a deterministic single value and financial evaluations are based on the estimated value. However, it does not provide a confidence on the estimate. The proposed model in this study assumes the truck maintenance cost is a stochastic parameter due to the significant level of uncertainty in the data and schedules the available fleet to meet the annual production targets. The scheduling has been performed by applying both the proposed stochastic and deterministic approaches. The approach provides a distribution for the maintenance cost of the optimized equipment schedule minimizing the cost.
first_indexed 2025-11-14T09:40:41Z
format Journal Article
id curtin-20.500.11937-49389
institution Curtin University Malaysia
institution_category Local University
last_indexed 2025-11-14T09:40:41Z
publishDate 2012
publisher Zhongguo Meitan Xuehui
recordtype eprints
repository_type Digital Repository
spelling curtin-20.500.11937-493892017-09-21T01:06:02Z Mining truck scheduling with stochastic maintenance cost Topal, Erkan Ramazan, S. Open pit mining operations utilize large scale and expensive equipment. For the mines implementing shovel and truck operation system, trucks constitute a large portion of these equipment and are used for hauling the mined materials. In order to have sustainable and viable operation, these equipment need to be utilized efficiently with minimum operating cost. Maintenance cost is a significant proportion of the overall operating costs. The maintenance cost of a truck changes non-linearly depending on the type, age and truck types. A new approach based on stochastic integer programming (SIP) techniques is used for annually scheduling a fixed fleet of mining trucks in a given operation, over the life of mine (multi-year time horizon) to minimize maintenance cost. The maintenance cost data in mining usually has uncertainty caused from the variability of the operational conditions at mines. To estimate the cost, usually historic data from different operations for new mines, and/or the historic data at the operating mines are used. However, maintenance cost varies depending on road conditions, age of equipment and many other local conditions at an operation. Traditional models aim to estimate the maintenance cost as a deterministic single value and financial evaluations are based on the estimated value. However, it does not provide a confidence on the estimate. The proposed model in this study assumes the truck maintenance cost is a stochastic parameter due to the significant level of uncertainty in the data and schedules the available fleet to meet the annual production targets. The scheduling has been performed by applying both the proposed stochastic and deterministic approaches. The approach provides a distribution for the maintenance cost of the optimized equipment schedule minimizing the cost. 2012 Journal Article http://hdl.handle.net/20.500.11937/49389 10.1007/s12404-012-0316-4 Zhongguo Meitan Xuehui restricted
spellingShingle Topal, Erkan
Ramazan, S.
Mining truck scheduling with stochastic maintenance cost
title Mining truck scheduling with stochastic maintenance cost
title_full Mining truck scheduling with stochastic maintenance cost
title_fullStr Mining truck scheduling with stochastic maintenance cost
title_full_unstemmed Mining truck scheduling with stochastic maintenance cost
title_short Mining truck scheduling with stochastic maintenance cost
title_sort mining truck scheduling with stochastic maintenance cost
url http://hdl.handle.net/20.500.11937/49389