Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries

A large number of projects around the world experience extensive delays; that is to say they go beyond initial time and cost estimates. There are various causes of delay in different countries including social, economical, political, environmental and religious issues. Severe weather conditions, hea...

Full description

Bibliographic Details
Main Authors: Alavi Toussi, Maryam, Whyte, Andrew
Other Authors: Vanissom Vimonsatit
Format: Conference Paper
Published: Research Publishing Services 2012
Subjects:
Online Access:http://hdl.handle.net/20.500.11937/37033
_version_ 1848754935054729216
author Alavi Toussi, Maryam
Whyte, Andrew
author2 Vanissom Vimonsatit
author_facet Vanissom Vimonsatit
Alavi Toussi, Maryam
Whyte, Andrew
author_sort Alavi Toussi, Maryam
building Curtin Institutional Repository
collection Online Access
description A large number of projects around the world experience extensive delays; that is to say they go beyond initial time and cost estimates. There are various causes of delay in different countries including social, economical, political, environmental and religious issues. Severe weather conditions, heavy rains and floods are the most important causes of delay in road construction projects in Central Africa; on the other hand, in the Middle East, many delays are due to ineffective planning, shortage of labour and workmanship, whilst in West Central Asia many constructional delays are caused by changing orders and owners financial constraints. The work presented here discusses the extent to which geographical location and socio-economic variables affect construction delay generally, and examines in particular the main reasons of delay (and a means to address and mitigate such delay) in construction projects in the Persian Gulf. The work explores key factors of delay related to reliance of construction budget(s) upon oil price in locations where 85% of the national construction and infrastructure budget is derived from the oil income, and where fluctuations in dollar-per-barrel costs have a knock-on effect for construction project interim payments and final accounting to allow practical completion; discussion is made (in this early-stage research-project discussion paper) of an accurate means to predict and then allocate risk and fluctuation allowances into both the pre-contract feasibility stage as well as on-site activities directed and controlled by contractual arrangement.
first_indexed 2025-11-14T08:48:18Z
format Conference Paper
id curtin-20.500.11937-37033
institution Curtin University Malaysia
institution_category Local University
last_indexed 2025-11-14T08:48:18Z
publishDate 2012
publisher Research Publishing Services
recordtype eprints
repository_type Digital Repository
spelling curtin-20.500.11937-370332023-02-07T08:01:20Z Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries Alavi Toussi, Maryam Whyte, Andrew Vanissom Vimonsatit Amarjit Singh Siamak Yazdani Oil Construction Delay Persian gulf A large number of projects around the world experience extensive delays; that is to say they go beyond initial time and cost estimates. There are various causes of delay in different countries including social, economical, political, environmental and religious issues. Severe weather conditions, heavy rains and floods are the most important causes of delay in road construction projects in Central Africa; on the other hand, in the Middle East, many delays are due to ineffective planning, shortage of labour and workmanship, whilst in West Central Asia many constructional delays are caused by changing orders and owners financial constraints. The work presented here discusses the extent to which geographical location and socio-economic variables affect construction delay generally, and examines in particular the main reasons of delay (and a means to address and mitigate such delay) in construction projects in the Persian Gulf. The work explores key factors of delay related to reliance of construction budget(s) upon oil price in locations where 85% of the national construction and infrastructure budget is derived from the oil income, and where fluctuations in dollar-per-barrel costs have a knock-on effect for construction project interim payments and final accounting to allow practical completion; discussion is made (in this early-stage research-project discussion paper) of an accurate means to predict and then allocate risk and fluctuation allowances into both the pre-contract feasibility stage as well as on-site activities directed and controlled by contractual arrangement. 2012 Conference Paper http://hdl.handle.net/20.500.11937/37033 Research Publishing Services restricted
spellingShingle Oil
Construction
Delay
Persian gulf
Alavi Toussi, Maryam
Whyte, Andrew
Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries
title Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries
title_full Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries
title_fullStr Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries
title_full_unstemmed Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries
title_short Factors Influencing Delay in Construction/Civil Engineering Projects in the Persian Gulf Countries
title_sort factors influencing delay in construction/civil engineering projects in the persian gulf countries
topic Oil
Construction
Delay
Persian gulf
url http://hdl.handle.net/20.500.11937/37033