Integrated short and medium term underground mine production scheduling

The development of short- and medium-term mine production schedules in isolation from each other has meant that only a local optimum can be achieved when each scheduling phase is carried out. The globally optimal solution, however, can be achieved when integrating scheduling phases and accounting fo...

Full description

Bibliographic Details
Main Authors: Nehring, M., Topal, Erkan, Knights, P., Kizil, M.
Format: Journal Article
Published: South African Institute of Mining and Metallurgy 2012
Subjects:
Online Access:http://www.saimm.co.za/Journal/v112n05p365.pdf
http://hdl.handle.net/20.500.11937/24263
_version_ 1848751379821101056
author Nehring, M.
Topal, Erkan
Knights, P.
Kizil, M.
author_facet Nehring, M.
Topal, Erkan
Knights, P.
Kizil, M.
author_sort Nehring, M.
building Curtin Institutional Repository
collection Online Access
description The development of short- and medium-term mine production schedules in isolation from each other has meant that only a local optimum can be achieved when each scheduling phase is carried out. The globally optimal solution, however, can be achieved when integrating scheduling phases and accounting for the interaction between short-term and medium-term activities simultaneously. This paper addresses the task of integrating short- and medium term production plans by combining the short-term objective of minimizing deviation from targeted mill feed grade with the medium-term objective of maximizing net present value (NPV) into a single mathematical optimization model. A conceptual sublevel stoping operation comprising 30 stopes is used for trialling segregated and integrated scheduling approaches. Segregated medium- and short-term scheduling using separate models achieved an NPV of $42 654 456. The final scheduling approach involved integrating the two scheduling horizons using the newly-developed globally optimal integrated production scheduling model to achieve an NPV of $42 823 657 with smoother mill feed grade. The larger the stope data set, the larger the difference between the two scheduling approaches is likely to be. At the very least, an integrated approach ensures feasibility across the two scheduling horizons, which cannot always be assumed when using a segregated approach.
first_indexed 2025-11-14T07:51:48Z
format Journal Article
id curtin-20.500.11937-24263
institution Curtin University Malaysia
institution_category Local University
last_indexed 2025-11-14T07:51:48Z
publishDate 2012
publisher South African Institute of Mining and Metallurgy
recordtype eprints
repository_type Digital Repository
spelling curtin-20.500.11937-242632017-01-30T12:41:58Z Integrated short and medium term underground mine production scheduling Nehring, M. Topal, Erkan Knights, P. Kizil, M. integrated scheduling mine planning optimization mixed integer programming production scheduling The development of short- and medium-term mine production schedules in isolation from each other has meant that only a local optimum can be achieved when each scheduling phase is carried out. The globally optimal solution, however, can be achieved when integrating scheduling phases and accounting for the interaction between short-term and medium-term activities simultaneously. This paper addresses the task of integrating short- and medium term production plans by combining the short-term objective of minimizing deviation from targeted mill feed grade with the medium-term objective of maximizing net present value (NPV) into a single mathematical optimization model. A conceptual sublevel stoping operation comprising 30 stopes is used for trialling segregated and integrated scheduling approaches. Segregated medium- and short-term scheduling using separate models achieved an NPV of $42 654 456. The final scheduling approach involved integrating the two scheduling horizons using the newly-developed globally optimal integrated production scheduling model to achieve an NPV of $42 823 657 with smoother mill feed grade. The larger the stope data set, the larger the difference between the two scheduling approaches is likely to be. At the very least, an integrated approach ensures feasibility across the two scheduling horizons, which cannot always be assumed when using a segregated approach. 2012 Journal Article http://hdl.handle.net/20.500.11937/24263 http://www.saimm.co.za/Journal/v112n05p365.pdf South African Institute of Mining and Metallurgy fulltext
spellingShingle integrated scheduling
mine planning
optimization
mixed integer programming
production scheduling
Nehring, M.
Topal, Erkan
Knights, P.
Kizil, M.
Integrated short and medium term underground mine production scheduling
title Integrated short and medium term underground mine production scheduling
title_full Integrated short and medium term underground mine production scheduling
title_fullStr Integrated short and medium term underground mine production scheduling
title_full_unstemmed Integrated short and medium term underground mine production scheduling
title_short Integrated short and medium term underground mine production scheduling
title_sort integrated short and medium term underground mine production scheduling
topic integrated scheduling
mine planning
optimization
mixed integer programming
production scheduling
url http://www.saimm.co.za/Journal/v112n05p365.pdf
http://hdl.handle.net/20.500.11937/24263