Statistical characteristics of cost contingency in water infrastructure projects

Cost contingency is one component of a project’s budget to cater for cost growth. The determination of a project’s cost contingency is a pervasive problem because the amount that is incorporated into an estimate is invariably insufficient to accommodate the cost growth of a project. This study analy...

Full description

Bibliographic Details
Main Authors: Baccarini, David, Love, Peter
Format: Journal Article
Published: American Society of Civil Engineers 2014
Online Access:http://hdl.handle.net/20.500.11937/17092
_version_ 1848749364842856448
author Baccarini, David
Love, Peter
author_facet Baccarini, David
Love, Peter
author_sort Baccarini, David
building Curtin Institutional Repository
collection Online Access
description Cost contingency is one component of a project’s budget to cater for cost growth. The determination of a project’s cost contingency is a pervasive problem because the amount that is incorporated into an estimate is invariably insufficient to accommodate the cost growth of a project. This study analyzed the statistical characteristics of cost contingency and cost growth experienced in 228 similar Australian water infrastructure projects that were procured by using traditional lump contracts. It was revealed that mean project final costs exceeded the approved budgets that contained contingency. The mean contingency percentage addition was 8.46%, yet the mean contingency required for the final cost was 13.58% for the sampled projects. Thus, the deterministic percentage addition, used by the sponsor to accommodate for cost growth beyond their baseline budget, was inaccurate. To improve the accuracy of a contingency estimate, the empirical distributions of cost contingency and cost performance were examined to determine their best-fit probability distribution. The research presented in this paper demonstrates that determining the best fit probability distribution provides a more robust and defendable basis for selecting a cost contingency than the traditional deterministic percentage approach.
first_indexed 2025-11-14T07:19:46Z
format Journal Article
id curtin-20.500.11937-17092
institution Curtin University Malaysia
institution_category Local University
last_indexed 2025-11-14T07:19:46Z
publishDate 2014
publisher American Society of Civil Engineers
recordtype eprints
repository_type Digital Repository
spelling curtin-20.500.11937-170922017-09-13T15:42:03Z Statistical characteristics of cost contingency in water infrastructure projects Baccarini, David Love, Peter Cost contingency is one component of a project’s budget to cater for cost growth. The determination of a project’s cost contingency is a pervasive problem because the amount that is incorporated into an estimate is invariably insufficient to accommodate the cost growth of a project. This study analyzed the statistical characteristics of cost contingency and cost growth experienced in 228 similar Australian water infrastructure projects that were procured by using traditional lump contracts. It was revealed that mean project final costs exceeded the approved budgets that contained contingency. The mean contingency percentage addition was 8.46%, yet the mean contingency required for the final cost was 13.58% for the sampled projects. Thus, the deterministic percentage addition, used by the sponsor to accommodate for cost growth beyond their baseline budget, was inaccurate. To improve the accuracy of a contingency estimate, the empirical distributions of cost contingency and cost performance were examined to determine their best-fit probability distribution. The research presented in this paper demonstrates that determining the best fit probability distribution provides a more robust and defendable basis for selecting a cost contingency than the traditional deterministic percentage approach. 2014 Journal Article http://hdl.handle.net/20.500.11937/17092 10.1061/(ASCE)CO.1943-7862.0000820 American Society of Civil Engineers restricted
spellingShingle Baccarini, David
Love, Peter
Statistical characteristics of cost contingency in water infrastructure projects
title Statistical characteristics of cost contingency in water infrastructure projects
title_full Statistical characteristics of cost contingency in water infrastructure projects
title_fullStr Statistical characteristics of cost contingency in water infrastructure projects
title_full_unstemmed Statistical characteristics of cost contingency in water infrastructure projects
title_short Statistical characteristics of cost contingency in water infrastructure projects
title_sort statistical characteristics of cost contingency in water infrastructure projects
url http://hdl.handle.net/20.500.11937/17092